Md. Code Ann., Real Prop. Title 9

Maryland Title 9 Mechanics Lien Auditor

Audit Maryland statutory deadlines: 120-day subcontractor notice to owner, 180-day Circuit Court judicial petition, and show cause proceedings.

Project & Claim Timeline
Under § 9-102(a), improvements to existing buildings only qualify if improved to the extent of 15% of the building's value.
$
Md. Code Ann., Real Prop. § 9-104 requires written notice to the owner within 120 days after work completion.
Judicial Audit Assessment
Click "Audit Maryland Statutory Deadlines" to calculate timeline.