Kansas Mechanics Lien K.S.A. Chapter 60 Statutory Auditor

Audit Kansas Statutes Annotated Chapter 60 Article 11 contractor deadlines: 3-month (sub) vs 4-month (prime) filings, warning statements, and 1-year lawsuits.
Kansas Statutes Annotated (K.S.A.) §§ 60-1101 - 60-1110

Statutory Audit Parameters

Compliance & Legal Finding

Statutory Questions & Legal Precedents

What is the difference between prime contractor and subcontractor lien deadlines in Kansas?

Under K.S.A. § 60-1102, an original/prime contractor must file a lien statement within 4 months after the last date labor or materials were furnished. Under K.S.A. § 60-1103, a subcontractor or supplier must file within 3 months after the last furnishing.

What is the Kansas residential warning statement requirement?

Under K.S.A. § 60-1103a, for residential property, a subcontractor or supplier cannot obtain a valid lien against a new residential property unless a statutory Warning Statement or Notice of Intent to Perform has been delivered or recorded prior to the passage of title.

How long does a claimant have to foreclose on a mechanics lien in Kansas?

Under K.S.A. § 60-1105, an action to foreclose a mechanics lien must be brought in district court within 1 year from the date the lien statement was filed.