Under Idaho Code § 45-507(2), all claimants (both general contractors and subcontractors) must file a claim of lien with the county recorder within 90 days after the completion of the labor or services or the furnishing of materials.
Under Idaho Code § 45-507(4), no later than twenty-four (24) hours after filing the claim of lien with the county recorder, the claimant must serve a copy of the claim on the owner either by personal delivery or certified mail.
Under Idaho Code § 45-510, a mechanics lien expires and becomes void unless judicial proceedings to foreclose are commenced in district court within six (6) months after the claim of lien was recorded.