Georgia Mechanics Lien Rights Auditor
Audit preliminary notices, 90-day claim of lien recording limits, and 365-day foreclosure suit requirements under O.C.G.A. § 44-14-361.
Georgia Statutory Lien Timeline & Audit
Notice to Contractor (NTC) Deadline
90-Day Claim of Lien Recording
Commencement of Action Deadline
| Claimant Status & Tier: | |
| Notice to Owner Post-Filing: | Copy of claim of lien must be sent to owner via certified mail ≤ 2 business days of recording |
| Preliminary Notice of Lien Rights: | |
| Notice of Commenced Action: | Lis Pendens / Notice of Action must be recorded ≤ 30 days after filing foreclosure lawsuit |
Georgia Code Benchmarks
- Notice to Contractor: If a Notice of Commencement is filed, subcontractors without direct privity must deliver a Notice to Contractor within 30 days of first furnishing or 30 days of NOC filing.
- Strict 90-Day Rule: Filing on day 91 is fatally defective and the lien is void ab initio.
- 365 Days to Sue: Lawsuit must be commenced within 365 calendar days from the date the lien was filed.