OSHA 29 CFR § 1910.147 Lockout/Tagout (LOTO) Auditor

Hazardous Energy Control Procedures, Zero-Energy State Verification, and Annual Periodic Audits

Machine Energy Isolation Profile

Statutory Determination & LOTO Mandates

Machine-Specific Written ECP Required: --
Lockout vs. Tagout Mandate: --
Zero-Energy State Verification Status: --

Annual Periodic Inspection Audit (§ 1910.147(c)(6))

Annual Audit Deadline (12-Month Rule): --
Inspection Compliance Status: --
Independent Authorized Inspector: Mandatory Non-User Inspector

Overall Safety & Citation Risk

OSHA Willful / Serious Citation Risk: --
Service & Maintenance Safety Rating: --

OSHA 29 CFR § 1910.147 Key Compliance Matrix

Statutory Provision Required Safety Action Mandatory OSHA Standard
§ 1910.147(c)(4) Machine-Specific Written ECP Specific written steps required unless 8 strict single-source exception criteria are met.
§ 1910.147(c)(2) Lockout Preference Lockout is mandatory whenever machinery is capable of being locked out.
§ 1910.147(d)(5) Stored Energy Dissipation All potentially hazardous stored or residual energy must be relieved, disconnected, or restrained.
§ 1910.147(d)(6) Zero Energy Verification Prior to starting work, authorized employee must verify that isolation has been accomplished.
§ 1910.147(c)(6) Annual Periodic Inspection Documented inspection of each procedure at least annually by an authorized non-user inspector.

Frequently Asked Regulatory Questions

What is the primary scope and purpose of OSHA 29 CFR § 1910.147?

OSHA 29 CFR § 1910.147 covers the servicing and maintenance of machines and equipment in which the unexpected energization or start up of the machines or equipment, or release of stored energy could cause injury to employees. It establishes minimum performance requirements for the control of hazardous energy (electrical, mechanical, hydraulic, pneumatic, chemical, thermal, and gravity).

When is a machine-specific written Energy Control Procedure (ECP) required?

Under § 1910.147(c)(4), employers must develop, document, and utilize specific procedures for the control of hazardous energy for every machine. An exception exists only if all 8 conditions in § 1910.147(c)(4)(i) are met (single energy source readily identified and isolated, no potential for stored energy, locked out with a single device, exclusive control of employee, and zero accidents).

What are the core steps to achieve a Zero Energy State under § 1910.147(d)?

The sequential order to achieve zero energy is: (1) Preparation for shutdown; (2) Machine or equipment shutdown; (3) Machine isolation from all energy sources; (4) Lockout or tagout device application; (5) Stored energy relief/dissipation (bleeding hydraulic/pneumatic pressure, discharging capacitors, blocking mechanical gravity); and (6) Verification of isolation (testing operating controls and verifying zero voltage).

What are the rules regarding Lockout vs. Tagout?

Under § 1910.147(c)(2), if an energy isolating device is capable of being locked out, the employer's energy control program must utilize lockout, unless the employer can demonstrate that the utilization of a tagout program will provide full employee protection equivalent to lockout. Tags alone must be supplemented with additional safety measures, such as removing an isolating circuit element or blocking a control switch.

How often must periodic inspections of LOTO procedures be conducted?

Under § 1910.147(c)(6), the employer must conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed. The inspection must be performed by an authorized employee other than the one(s) utilizing the procedure, including a review between the inspector and authorized employees.