EPA Clean Air Act & NSR Preconstruction Permitting (40 CFR § 52.21)

EPA Clean Air Act NSR / PSD Major Modification Modeler

Model the 2-step major modification test under 40 CFR § 52.21, baseline actual to projected actual emissions, EPA Significant Emission Rates (SER), contemporaneous 5-year netting, and BACT/LAER triggers.

Facility & Emissions Parameters

Emissions existing unit could have accommodated during baseline period.
Permanent, enforceable emissions decreases within 5-year netting window.

Statutory Permitting Audit Results

Minor Modification (Synthetic Minor / Below SER)
Statutory SER Threshold: 40.0 TPY
Step 1 Project Emissions Increase: 42.0 TPY (Exceeds SER)
Step 1 Trigger Status: Significant Increase Triggered
Step 2 Net Emissions Increase (Netting): 32.0 TPY (Below 40.0 TPY SER)
Major Modification Trigger Status: NOT A MAJOR MODIFICATION (Netted Out)
Mandated Pollution Control Tech: State Minor NSR Standards

EPA Clean Air Act Compliance Analysis

Although the project alone resulted in a 42.0 TPY increase exceeding the 40.0 TPY SER threshold in Step 1, the facility successfully 'netted out' in Step 2 by crediting 10.0 TPY in contemporaneous reductions, resulting in a net emissions increase of 32.0 TPY (< 40.0 TPY SER). Major NSR/PSD preconstruction permitting is avoided.

EPA Clean Air Act NSR / PSD Regulatory FAQ

What is 'Project Emissions Accounting' under EPA's 2020 NSR reforms?
Project Emissions Accounting allows an existing major source to consider both emissions increases and emissions decreases resulting from a single project at Step 1 of the NSR applicability test. If the net project emissions at Step 1 do not exceed the SER threshold, the project does not cause a significant emissions increase and the review ends without needing a Step 2 contemporaneous netting analysis.
What is the difference between BACT and LAER?
Best Available Control Technology (BACT) applies under the PSD program in attainment areas and balances energy, environmental, and economic impacts (costs) in determining the top-down control level. Lowest Achievable Emission Rate (LAER) applies under Nonattainment NSR and mandates the most stringent emission limitation achieved in practice or in any state implementation plan (SIP), without consideration of economic cost.
What records must be kept if a facility projects no major modification?
Under 40 CFR § 52.21(r)(6), if a project has a 'reasonable possibility' of resulting in a significant emissions increase (typically when projected increases exceed 50% of the SER threshold), the facility must document pre-project emissions projections and track and report actual emissions annually for 5 years (or 10 years if the project increases the design capacity or potential to emit).
Can a facility accept synthetic minor permit limits to avoid NSR?
Yes. A major stationary source may accept legally and practically enforceable permit conditions (such as limits on fuel consumption, hours of operation, or raw material throughput) that restrict its potential to emit below the SER threshold, thereby avoiding Major NSR/PSD review.