← Back to OmniCalc Hub
Clean Water Act § 402 & 40 CFR § 122.26

EPA Stormwater CGP & SWPPP Compliance Auditor

Statutory Compliance Auditor for Clean Water Act § 402, 40 CFR § 122.26 & EPA 2022/2027 CGP: 1-Acre Disturbance Thresholds, 14-Day eNOI Windows, Weekly Site Inspections, and Civil Penalties

Construction Site & Disturbance Details

1.0 acre threshold triggers mandatory NPDES stormwater coverage.
Sites under 1 acre are covered if cumulative common plan reaches 1 acre.
Requires twice-weekly or 7-day + storm event inspection intervals.
Electronic Notice of Intent (eNOI) must be submitted 14 days prior.
Used to model Clean Water Act statutory maximum penalty exposure.

Permit Audit Findings & Deadlines

CGP Stormwater Permit Status: Coverage Mandatory
Soil Disturbance Threshold: 4.50 Acres ($\ge$ 1.0 Acre Rule)
Certified SWPPP Requirement: Mandatory Prior to eNOI Filing
EPA eNOI Submittal Cutoff: -
Mandatory Inspection Frequency: Every 7 Calendar Days
Rain Gauge Trigger Threshold: 0.25 Inches in 24 Hours
Temporary Stabilization Window: 14 Calendar Days of Ceasing Work
CWA Maximum Civil Penalty Rate: $66,712 / day per violation
Maximum Civil Penalty Exposure: $0.00

EPA CGP Milestone Checklist

• Step 1: Prepare and certify comprehensive site-specific SWPPP.

• Step 2: Submit eNOI via NeT-CGP at least 14 days before groundbreaking.

• Step 3: Install perimeter sediment controls (silt fence, wattles) prior to earthwork.

• Step 4: Document inspections and corrective actions within 24 hours.

Environmental Practice Note: Under Clean Water Act § 309(c), negligent or knowing violations of NPDES stormwater permits carry criminal liability in addition to civil penalties of up to $66,712 per day. Operators must retain a certified copy of the SWPPP on-site or in an accessible field vehicle, along with signed inspection logs for at least 3 years following permit termination.

EPA Stormwater CGP Frequently Asked Questions

When is an EPA Construction General Permit (CGP) legally required under the Clean Water Act? +
What is the statutory deadline for submitting the Notice of Intent (eNOI) and preparing the SWPPP? +
What are the mandatory inspection schedules under the EPA CGP? +
What are the legal stabilization timelines and Clean Water Act civil penalties for non-compliance? +