Can multiple small wetland impacts be combined to avoid the 0.50-acre cap? +
No. Under 33 CFR ยง 330.6(d), piecemealing or segmenting an overall project to meet nationwide permit thresholds is strictly prohibited; the Corps evaluates the single and complete project.
When is compensatory mitigation required under Section 404? +
Under General Condition 23, compensatory mitigation is generally required for all wetland losses exceeding 1/10 acre (0.10 acre) to ensure no net loss of aquatic functions and values.
What happens if work begins before the 45-day PCN clock expires? +
Discharging dredged or fill material into WOTUS without permit authorization violates Clean Water Act Section 301, subjecting the developer to EPA/USACE stop-work orders, restoration mandates, and civil penalties exceeding $64,000 per day of violation.