Clean Water Act NPDES Stormwater CGP Auditor

Audit environmental compliance under 40 CFR § 122.26 and EPA 2022 CGP: 1-acre disturbance thresholds, 14-day NOI waiting periods, SWPPP certifications, stormwater inspections, and $59,973/day penalties.

Total earth disturbance (1.0+ acres triggers CGP).
Counts total cumulative disturbance of common development.
Trigger enhanced inspection and stabilization standards.
SWPPP must be signed and certified BEFORE NOI submission.
Date eNOI submitted via EPA NeT-CGP portal.
EPA CGP Part 4 mandatory inspection schedules.
CGP Compliance Approved
Permit Coverage Mandate
Mandatory NPDES CGP
Authorized Earthwork Date
14 Days Post-NOI
Inspection Compliance
Compliant
Stabilization Deadline
14 Calendar Days
Notice of Termination (NOT) Criteria
70% Perennial Cover
Max Civil Penalty Exposure
$59,973 / Day / Violation

Clean Water Act NPDES CGP Guidance

What acreage of disturbance triggers Clean Water Act NPDES stormwater permit coverage?
Under Clean Water Act § 402(p) and 40 CFR § 122.26, stormwater discharges associated with construction activity require NPDES permit coverage if the project disturbs one (1.0) or more acres of land, or less than one acre if part of a larger common plan of development or sale that ultimately disturbs 1.0 or more acres.
What is the mandatory waiting period after submitting a Notice of Intent (NOI)?
Under the EPA 2022 Construction General Permit (CGP) Part 1.4, an operator must submit an electronic Notice of Intent (eNOI) at least fourteen (14) calendar days prior to commencing any earth-disturbing activities. If discharging to a Tier 3 Outstanding National Resource Water or waterbody impaired for sediment or nutrients, a 30-calendar-day review period applies before authorization is granted.
What are the federal civil penalties for non-compliance with the NPDES CGP?
Under Clean Water Act Section 309(d), as adjusted for inflation by the Federal Civil Penalties Inflation Adjustment Act, failure to obtain permit coverage, failure to maintain an adequate SWPPP, or unpermitted stormwater discharges can result in civil judicial penalties of up to $59,973 per day per violation, plus administrative penalties and potential criminal enforcement for knowing violations.