Clean Air Act § 112(r) Risk Management Plan (RMP) Auditor | 40 CFR Part 68
Audit Clean Air Act Section 112(r) and EPA Chemical Accident Prevention Provisions under 40 CFR Part 68: determine Program 1, 2, or 3 applicability for toxic and flammable substances above Threshold Quantities (TQ), worst-case release scenario hazard assessments, 5-year RMP update cycles, and civil enforcement penalties up to $121,275 per day.
Statutory requirement: Update every 5.0 years
Statutory & Regulatory Guidance
Under 40 CFR § 68.10, an owner or operator of a stationary source that has more than a Threshold Quantity (TQ) of a regulated toxic or flammable substance listed in 40 CFR § 68.130 in a process must comply with the Risk Management Program regulations. Common covered substances include anhydrous ammonia (TQ 10,000 lbs), chlorine (TQ 2,500 lbs), propane (TQ 10,000 lbs), and aqueous ammonia >= 20% (TQ 20,000 lbs).
The three program levels are: (1) Program 1: Processes with no offsite public receptors in the worst-case release zone and no accidental releases with offsite impacts in the past 5 years (minimal requirements); (2) Program 3: Processes in specific industrial NAICS codes (chemicals, refineries, paper) or subject to OSHA Process Safety Management (PSM 29 CFR 1910.119); and (3) Program 2: All other covered processes not meeting Program 1 or Program 3 criteria.
Under 40 CFR § 68.190, a covered facility must submit an initial RMP before a regulated substance is present above the threshold, and must update and re-submit the RMP at least once every five (5) years, or within six months of any major process change. Civil penalties under CAA Section 113 (42 U.S.C. § 7413) can reach up to $121,275 per day per violation.