Environmental & Workplace Safety Law

EPA Clean Air Act Asbestos NESHAP Compliance Auditor | 40 CFR Part 61

Audit facility renovation and demolition under Clean Air Act Section 112 and EPA Asbestos NESHAP (40 CFR Part 61, Subpart M): RACM threshold quantities (260 linear ft / 160 sq ft / 35 cu ft), 10-working-day advance notice, certified survey, and civil penalties up to $121,275/day.


Frequently Asked Statutory Questions

Under 40 CFR § 61.145(a)(1), the Asbestos NESHAP applies if the combined amount of RACM to be stripped, removed, dislodged, or disturbed during a renovation or demolition project is at least: (1) 260 linear feet (80 linear meters) on pipes; (2) 160 square feet (15 square meters) on other facility components; or (3) 35 cubic feet (1 cubic meter) off facility components where the length or area could not be measured previously.

Under 40 CFR § 61.145(b), the owner or operator must provide written notification to the EPA Regional Administrator or delegated state agency at least ten (10) working days (not calendar days) BEFORE asbestos stripping, removal, or demolition begins. Demolitions ALWAYS require notification, even if zero asbestos is present.

Under Clean Air Act Section 113(b) (42 U.S.C. § 7413(b)) and the EPA Civil Monetary Penalty Inflation Adjustment Rule, violations of Asbestos NESHAP regulations carry statutory civil penalties of up to $121,275 per day per violation. Criminal penalties (fines and imprisonment up to 5 years) apply for knowing violations under Section 113(c).