Wyo. Stat. Title 29 Construction Law

Wyoming Mechanics' Lien Statutory Compliance Auditor

Audit statutory deadlines under Wyoming Title 29. Calculate contractor 150-day and subcontractor 120-day recording windows, 20-day notice of intent, 30-day preliminary notice, and 180-day lawsuit limitations.

Project Milestones & Notices 🏗️

Trigger for 30-day preliminary Notice to Owner under Wyo. Stat. § 29-2-112.
Critical baseline for the 150-day / 120-day recording deadline (§ 29-1-311).
Mandatory 20-day prior notice under § 29-2-107 before recording.
Recording with the County Clerk in the county where property is located.

Statutory Audit Schedule 📅

AUDITING WYOMING LIEN...
1. Preliminary Notice to Owner (§ 29-2-112) TBD
Must be served by subcontractors within 30 days of first furnishing labor/materials.
2. Notice of Intention to File Lien (§ 29-2-107) TBD
Must be served on property owner at least 20 days prior to recording the lien statement.
3. County Clerk Lien Recording Deadline (§ 29-1-311) TBD
Hard statutory limit: 150 days for general contractors, 120 days for subcontractors from last work.
4. Lawsuit Foreclosure Deadline (§ 29-2-109) TBD
Must file complaint in Wyoming District Court within 180 days of lien statement recording date.

Wyoming Construction Lien Law FAQs

What is the recording deadline for a Wyoming mechanics' lien?
Under Wyo. Stat. Ann. § 29-1-311(a), a contractor asserting a lien must record a lien statement with the county clerk within 150 days from the date when the last work was performed or material furnished. For subcontractors, materialmen, or laborers, the recording deadline is 120 days from the date last work was performed or materials supplied.
Is a preliminary notice required in Wyoming prior to filing a lien?
Yes. Under Wyo. Stat. § 29-2-112, subcontractors and material suppliers must send a preliminary Notice to Owner within 30 days of first furnishing services or materials. Furthermore, under § 29-2-107, ALL claimants (contractors and subcontractors) must send a formal Notice of Intention to File Lien to the property owner at least 20 days before recording the lien statement.
What is the statute of limitations to enforce a mechanics' lien in Wyoming?
Under Wyo. Stat. Ann. § 29-2-109, a lawsuit to foreclose a mechanics' lien must be commenced in district court within 180 days (6 months) after the date the lien statement was recorded with the county clerk. If no action is commenced within 180 days, the lien is statutorily extinguished and void.
Where must the lien statement be recorded in Wyoming?
The verified lien statement must be filed in the office of the county clerk of the county in which the real property, building, or improvement is situated. Within 30 days after filing, the claimant must send a copy of the recorded statement to the property owner by certified mail under § 29-1-311(c).