60-Day Identification Notices, Mandatory 30-Day Notice of Intent, and 6-Month Recording Limits
| Statutory Step | Governing Statute | Mandatory Timing Protocol |
|---|---|---|
| 60-Day Identification Notice | Wis. Stat. § 779.02(2)(b) | Within 60 days of first furnishing labor/materials on residential projects under 4 units. |
| 30-Day Notice of Intent to File | Wis. Stat. § 779.02(2)(b) | Must serve on owner at least 30 days BEFORE filing the claim for lien with circuit court. |
| Claim of Lien Recording | Wis. Stat. § 779.06(1) | Within 6 months after claimant last performed labor or furnished materials. |
| Foreclosure Lawsuit | Wis. Stat. § 779.06(1) | Within 2 years from date of filing claim for lien with the clerk of circuit court. |
| Theft by Contractor Liability | Wis. Stat. § 779.02(5) / § 895.446 | Misappropriation of construction loan/contract funds triggers criminal theft and civil treble damages. |
Under Wis. Stat. § 779.02(2)(b), every person other than a prime contractor who wishes to preserve a lien must serve on the owner a written notice of intent to file a lien claim at least 30 days before filing the claim with the clerk of circuit court. Filing a lien claim without providing this mandatory 30-day notice is a fatal jurisdictional defect invalidating the entire lien.
Under Wis. Stat. § 779.02(2)(b), subcontractors, laborers, and material suppliers must furnish a preliminary written identification notice to the owner within 60 days of first furnishing labor or materials on projects involving residential dwellings (under 4 units). Failure to give this 60-day notice forfeits lien rights unless an exception applies.
Under Wis. Stat. § 779.06(1), the claim for lien must be filed with the clerk of circuit court in the county where the real estate is located within 6 months after the claimant last performed labor or furnished materials for the improvement.
Under Wis. Stat. § 779.06(1), a lawsuit to foreclose the construction lien must be commenced within 2 years from the date the claim for lien was filed with the clerk of circuit court. Failure to file suit within this 2-year statutory period automatically extinguishes the lien by operation of law.
Under Wis. Stat. § 779.02(5), all moneys paid to any prime contractor or subcontractor for improvements upon real estate constitute a statutory trust fund. Using these funds for any purpose other than paying claims of laborers and materialmen before all claims are satisfied constitutes theft by contractor, carrying criminal penalties under § 943.20 and civil liability for treble damages plus attorney fees under § 895.446.