Washington State RCW 60.28 Public Works Retainage Auditor
Audit compliance with Washington Public Works Lien statutes (RCW Chapter 60.28 and RCW 39.08), calculate 5% retainage reserves, evaluate the strict 45-day claim window after formal acceptance, and verify state tax lien priorities.
Mandatory Washington Public Works Formalities
Statutory & Regulatory FAQs
What is the statutory retainage requirement on Washington public works contracts under RCW 60.28.011?
Under RCW 60.28.011(1)(a), public bodies in Washington must reserve a contract retainage of up to 5% from all moneys earned by the contractor on public works projects as a trust fund for the payment of labor, material suppliers, and state excise taxes.
What is the statutory deadline for subcontractors and suppliers to file a retainage claim?
Under RCW 60.28.011(2), a claimant must file a written notice of claim with the public agency within 45 days after the completion and formal acceptance of the project by the governing body of the public agency.
What priority do state tax liens have against public works retainage under RCW 60.28.040?
Under RCW 60.28.040, the amount of all taxes, increases, and penalties due from the contractor under Title 82 (Department of Revenue), Title 50 (Employment Security Department), and Title 51 (Labor & Industries) constitute a prior and paramount lien upon the entire retainage fund, having absolute priority over all other lien claimants.
What is the statute of limitations to enforce a claim against retainage in Washington?
Under RCW 60.28.030, an action to foreclose a lien on the retainage fund must be commenced in Superior Court within four months after filing the notice of claim. If no action is brought within four months, the claim against the retainage fund is extinguished.