Utah SCR Mechanics' Lien Auditor

Utah State Construction Registry & Title 38 Chapter 1a Engine

Hub Home

SCR Filing & Contract Data

Statutory Deadlines & Priority

SCR Preliminary Notice Compliant

Full lien rights preserved for all labor and materials furnished.

--
County Recorder Deadline
--
Days Remaining to Record
--
180-Day Lawsuit Deadline (§ 38-1a-701)
Full Priority
Lien Scope & Protection
🏠 Home Hub

Frequently Asked Questions

What is the mandatory preliminary notice on the Utah State Construction Registry (SCR)?

Under Utah Code Ann. § 38-1a-501, any person who desires to claim a construction lien must electronically file a preliminary notice on the Utah State Construction Registry (SCR) within twenty (20) calendar days after commencing work or first providing materials. Filing after 20 days limits lien rights to work furnished starting 5 days after the late filing.

What is the recording deadline for a Utah mechanics lien?

Under Utah Code Ann. § 38-1a-502, a claimant must record a written and verified Notice of Construction Lien in the County Recorder's office within 180 calendar days after the date on which final completion of the original contract occurs, or 90 days if a Notice of Completion is filed on the SCR.

What is the deadline to file a foreclosure lawsuit to enforce a Utah mechanics lien?

Under Utah Code Ann. § 38-1a-701, a claimant must file an action to enforce the lien in district court and record a Notice of Lis Pendens in the County Recorder's office within 180 calendar days after recording the Notice of Construction Lien.