Utah Mechanics' Lien & SCR Compliance Auditor | Utah Code § 38-1a

Audit Utah mechanics' and construction lien compliance under Utah Code Ann. Title 38, Chapter 1a: mandatory State Construction Registry (SCR) 20-day Preliminary Notice (§ 38-1a-501), 180-day Notice of Construction Lien recording with the County Recorder (§ 38-1a-502), and 180-day foreclosure lawsuit limitation period in District Court with recorded lis pendens (§ 38-1a-701).

Statutory Compliance Frequently Asked Questions

Under Utah Code Ann. § 38-1a-501, all contractors, subcontractors, and suppliers must file a preliminary notice on the electronic State Construction Registry (SCR) within twenty (20) days after commencement of their work or first furnishing of materials. A preliminary notice filed after 20 days is effective only for work performed or materials furnished five (5) days after the date on which the notice is filed.

Under Utah Code Ann. § 38-1a-502, a claimant must record a written Notice of Construction Lien with the County Recorder of the county in which the real property is located within one hundred eighty (180) days after the date on which final completion of the original contract occurs (or 90 days after a Notice of Completion is filed under § 38-1a-507).

Under Utah Code Ann. § 38-1a-701, an action to enforce a construction lien must be commenced in District Court within one hundred eighty (180) days after the day on which the claimant files the Notice of Construction Lien for record. The claimant must also file a notice of lis pendens with the County Recorder within that same 180-day period.