Texas Construction Law FAQs
What is the mandatory statutory retainage requirement in Texas?
Under Texas Property Code § 53.101, an owner of property under an original construction contract must retain 10 percent of the contract price or 10 percent of the value of the work during the progress of work and for 30 days after the work is completed. This statutory retainage fund exists to secure lien claimants.
What is the deadline for a subcontractor to perfect a retainage lien claim in Texas?
Under Tex. Prop. Code § 53.103 and recent statutory revisions, a claimant must send notice of contractual retainage to the owner and original contractor and file a lien affidavit with the county clerk no later than the 15th day of the third month following the month in which the original contract was completed, terminated, or abandoned.
What personal liability arises under the Texas Construction Trust Fund Act (Chapter 162)?
Under Texas Property Code Chapter 162, construction payments made to a contractor or subcontractor are deemed trust funds for the benefit of laborers and materialmen. An officer, director, or agent who intentionally or knowingly misapplies trust funds without paying beneficiaries faces personal non-dischargeable civil liability and criminal penalties up to a third-degree felony.