Calculate exact statutory lien recording deadlines for general contractors in direct privity with property owners. Covers commercial (4th month) and residential (3rd month) deadlines under HB 2237 updates.
🏗️ Contract & Completion Details
Determines whether 4-month or 3-month statutory window applies.
What is the lien filing deadline for an original contractor in Texas?
Under Texas Property Code § 53.052(a), an original contractor on a commercial project must file an affidavit claiming a lien by the 15th day of the 4th calendar month after the month in which the contract was completed, terminated, or abandoned. For residential construction projects, the deadline is the 15th day of the 3rd calendar month under § 53.052(b).
Do original contractors in Texas have constitutional lien rights?
Yes. Under Article XVI, Section 37 of the Texas Constitution, original contractors who contract directly with the owner hold a self-executing constitutional lien. Unlike statutory liens, this constitutional lien requires no affidavit filing to be valid against the original owner, though filing a statutory affidavit is critical to protect priority against third-party buyers or lenders.
What notice must an original contractor give after filing a lien in Texas?
Under Tex. Prop. Code § 53.055, the contractor must send a copy of the affidavit to the owner's last known business or residence address by certified or registered mail not later than the 1st business day after the date the affidavit is filed with the county clerk.