Texas Property Code Chapter 53 Statutory Retainage & Lien Fund Auditor
Audit Texas 10% statutory retainage obligations under Tex. Prop. Code § 53.101, owner personal liability under § 53.105, and retainage lien perfection deadlines under § 53.103.
Statutory Provisions & Frequently Asked Questions
What is the mandatory 10% statutory retainage under Texas Property Code § 53.101?
Under Texas Property Code § 53.101, during the progress of work under an original contract for which a mechanics lien may be claimed, and for 30 days after the work is completed, the property owner must retain 10% of the contract price or 10% of the value of the work to secure statutory lien claimants.
What is the owner's personal liability under Section 53.105 if retainage is not withheld?
If the owner fails or refuses to retain the required 10% under Section 53.101, claimants who comply with statutory notice and filing requirements have a valid lien against the property at least to the extent of the amount that should have been retained, and the owner is personally liable for that amount under Tex. Prop. Code § 53.105.
What is the deadline for filing a lien for unpaid retainage in Texas?
Following Texas legislative reforms (effective Jan 1, 2022), under Tex. Prop. Code § 53.052(d), a claimant claiming a lien for contractual retainage must file the lien affidavit not later than the 15th day of the third month (or second month for residential projects) after the month in which the original contract was completed, terminated, or abandoned.