Texas Property Code Chapter 53 Specially Fabricated Materials Lien Notice Auditor

Statutory Notice Deadlines under Tex. Prop. Code § 53.058, Fund Trapping Mechanics & Lien Affidavit Filing Deadlines

1. Project & Order Parameters

2. Notice Compliance Checklist

Statutory Deadlines & Lien Protection

COMPLIANT & PROTECTED
Notice deadlines and statutory prerequisites satisfied under Tex. Prop. Code § 53.058.
§ 53.058 Order Acceptance Notice Deadline: June 15, 2026
§ 53.052 Lien Affidavit Filing Deadline: July 15, 2026
Claim Amount Protected: $85,000
Trapped Owner Funds Status: TRAPPED AT RECEIPT

Statutory Analysis & Warnings

Undelivered Goods Lien Right: PRESERVED BY § 53.058
Notice Delivery Rule: Certified Mail / Overnight Trackable
Weekend / Holiday Rollover: Applies (Tex. Gov Code § 311.014)

Texas Property Code Chapter 53 Legal Framework for Custom Fabrication

Under Texas Property Code § 53.058, suppliers and fabricators of materials customized specifically for a construction project enjoy special protections. Unlike standard off-the-shelf lumber or hardware, which must be actually delivered and incorporated into the real property to support a lien, specially fabricated materials can support a mechanic's lien even if the goods are never delivered due to the owner's or general contractor's wrongful termination or project cancellation.

Mandatory Statutory Prerequisites:

Trapping Funds from Owner: Service of this notice obligates the property owner under § 53.081 to retain funds from the original contractor to satisfy the claim. Failure of the owner to trap funds makes the owner personally liable and subjects the property to foreclosure up to the trapped amount.

Frequently Asked Questions (Texas Property Code § 53.058)

What constitutes 'specially fabricated material' under Texas Property Code § 53.058?

Under Texas Property Code § 53.001(12) and § 53.058, specially fabricated material is material fabricated for use as a component of the construction or repair so as to be reasonably unsuitable for use elsewhere. This includes custom architectural millwork, fabricated structural steel, custom precast concrete, and custom glazing.

What is the statutory notice deadline under Texas Property Code § 53.058?

Under Texas Property Code § 53.058, the claimant must give notice to the property owner (and original contractor if claimant is a second-tier subcontractor) not later than the 15th day of the third month after the month in which the claimant received and accepted the order for the material.

Can a supplier file a lien if the specially fabricated materials are never delivered?

Yes. One of the prime benefits of § 53.058 is that if the required preliminary notice of order acceptance is timely given, the claimant has a valid mechanic's lien right against the owner's property even if the custom material is never delivered or incorporated into the improvement due to owner or contractor breach.

What additional notices are required if the material is actually delivered?

If the specially fabricated material is subsequently delivered to the project site, the claimant must also satisfy the standard Texas Property Code § 53.056 fund trapping notice requirements (giving notice to owner and contractor by the 15th day of the 3rd month following the month of delivery).

What is the deadline to file the mechanic's lien affidavit under Texas Property Code § 53.052?

For commercial projects, the lien affidavit must be filed with the county clerk not later than the 15th day of the fourth month after the month in which indebtedness accrued. For residential projects, it must be filed not later than the 15th day of the third month.