Tennessee Construction & Mechanics Lien Law

Tennessee TCA § 66-11-145 Notice of Nonpayment & Lien Auditor

Statutory Authority: Tenn. Code Ann. § 66-11-145 & § 66-11-115
Under Tennessee Code Annotated (TCA) § 66-11-145, a remote contractor (subcontractor or material supplier without direct privity with the owner) must serve a statutory Notice of Nonpayment within ninety (90) days from the end of each month in which labor or materials were provided. Failure to timely serve the Notice of Nonpayment completely forfeits lien rights for that month's work. Following completion, a Notice of Lien must be recorded within 90 days under TCA § 66-11-115, followed by a foreclosure action within 1 year under § 66-11-106.

Parameters & Input

Calendar date labor or materials were furnished.
Registered mail or personal service date.
Date the overall improvement was substantially completed.
Date recorded with the county register.

Compliance Determination

Auditing Tennessee Mechanics' Lien Timelines...
Calculating month-end 90-day nonpayment notice, 90-day recording, and 1-year enforcement.
Applicable Month-End Reference Date--
90-Day Notice of Nonpayment Deadline (§ 66-11-145)--
Notice of Nonpayment Service Finding--
90-Day Post-Completion Recording Deadline--
County Register Recording Timeliness--
1-Year Enforcement Lawsuit Deadline (§ 66-11-106)--
Overall Tennessee Lien Validity--

Statutory Questions & Legal Precedents

Every remote contractor (any contractor, subcontractor, or materialman not in direct contractual privity with the property owner) must serve a Notice of Nonpayment on both the property owner and the prime contractor on commercial and residential projects.

The notice must be served within ninety (90) days from the END OF THE CALENDAR MONTH in which the labor, services, or materials were provided. For example, for work done on October 5th, the 90-day period begins from October 31st, not October 5th.

Under TCA § 66-11-145(a), the notice must specify: (1) name of claimant and contracting party, (2) hand delivery or registered mail to owner and prime contractor, (3) amount unpaid, (4) description of the property, and (5) description of the work, materials, or equipment provided.

Under TCA § 66-11-115, a remote contractor must record a Notice of Lien in the county register of deeds within ninety (90) days after completion of the improvement, and commence an action to enforce the lien by attachment within one (1) year after recording.