South Dakota Mechanics' & Materialmen's Lien Auditor | SDCL Chapter 44-9
Audit South Dakota mechanics' and materialmen's lien statutory compliance under SDCL Chapter 44-9: 120-day verified statement of lien recording with the Register of Deeds (§ 44-9-15), post-recording notice to property owner personally or via certified mail, 6-year foreclosure lawsuit limitation period (§ 44-9-24), and owner 30-day demand to sue forfeiture rules (§ 44-9-26).
Statutory Compliance Frequently Asked Questions
Under SDCL § 44-9-15, the claimant must file a verified statement of lien with the Register of Deeds of the county in which the improved premises are situated within one hundred twenty (120) days after the date of the claimant's last labor, services, material, or machinery furnished.
Under SDCL § 44-9-15, a copy of the lien statement must be served upon the property owner personally or by registered or certified mail with return receipt requested. If served by mail, an affidavit of mailing must be recorded with the Register of Deeds.
Under SDCL § 44-9-24, an action to enforce the lien must be commenced in Circuit Court within six (6) years after the date of the last item of work. However, under SDCL § 44-9-26, the property owner may serve written demand on the claimant requiring commencement of suit within thirty (30) days; failure to sue within 30 days forfeits the lien.