Pennsylvania Mechanics' Lien Law 30-Day Formal Notice & Recording Auditor | 49 P.S. § 1101
Audit Pennsylvania Mechanics' Lien Law: 30-day Formal Notice of Intent (49 P.S. § 1501), 6-month Prothonotary filing (§ 1502), mandatory affidavit of service, and 2-year Scire Facias.
Statutory Provisions & Frequently Asked Questions
What is the mandatory 30-day Formal Notice of Intent under 49 P.S. § 1501?
Under Section 501 of the Pennsylvania Mechanics' Lien Law of 1963 (49 P.S. § 1501(b)), a subcontractor must serve a formal written Notice of Intent to File a Claim on the property owner at least 30 calendar days before filing the lien claim with the Prothonotary. The notice must state the claimant's name, contract details, description of the property, last date of work, and the amount claimed.
What is the strict rule regarding the Affidavit of Service under 49 P.S. § 1502?
Under 49 P.S. § 1502(a)(2), after filing the lien claim with the Prothonotary, the claimant must serve written notice of filing on the owner within 30 days, AND must file an Affidavit of Service with the Prothonotary within 20 days after service. Under settled Pennsylvania Supreme Court precedent (Day & Zimmermann, Inc. v. Blocked Iron Corp.), failure to strictly file the affidavit within 20 days completely invalidates the lien with no possibility of cure.
What is a Writ of Scire Facias in Pennsylvania mechanics lien law?
In Pennsylvania, filing a mechanics lien with the Prothonotary merely records the encumbrance. To obtain an enforceable monetary judgment and foreclose, the claimant must commence an action by obtaining a Writ of Scire Facias sur mechanics' lien claim under 49 P.S. § 1701 within 2 years from the date the lien claim was filed.