Oregon ORS Chapter 87 Construction Lien Auditor
Audit construction lien validity and enforceability under Oregon Revised Statutes Chapter 87, verify pre-lien notice compliance (ORS 87.093 / 87.021), track the 75-day county recording window, and enforce the 120-day circuit court foreclosure deadline.
Mandatory Oregon Procedural Milestones
Statutory & Regulatory FAQs
What is Oregon's Information Notice to Owner requirement under ORS 87.093?
Under ORS 87.093, a contractor who enters into a direct residential construction contract exceeding $2,000 with an owner must deliver an 'Information Notice to Owner About Construction Liens' at the time of signing or within five business days. Failure to deliver this statutory notice completely forfeits all mechanics lien rights under Oregon law.
When must subcontractors and suppliers send a Notice of Right to a Lien under ORS 87.021?
Under ORS 87.021, any person performing labor, providing services, or furnishing materials who does not have a direct contract with the owner must deliver a written Notice of Right to a Lien to the owner and mortgagees. The notice may be delivered at any time during the project, but it only protects labor and materials provided beginning eight business days prior to delivery of the notice.
What is the statutory deadline for recording a construction lien in Oregon?
Under ORS 87.035, a construction lien must be recorded in the county clerk's lien records within 75 days after the claimant ceased to furnish labor, rent equipment, or supply materials, or 75 days after completion of construction, whichever is earlier.
What is the statute of limitations to file a lien foreclosure lawsuit in Oregon?
Under ORS 87.055, a construction lien is valid for only 120 days after recording. A lawsuit to foreclose the lien must be commenced in circuit court within that 120-day period. Additionally, under ORS 87.057, a claimant must mail a formal written Notice of Intent to Foreclose to the owner and mortgagees at least 10 days before filing the lawsuit.