Ohio Mechanics Lien Notice of Furnishing & Affidavit Auditor | ORC Chapter 1311

Audit statutory deadlines under Ohio Revised Code Chapter 1311: 21-day Notice of Furnishing, 75-day commercial Affidavit of Lien, 30-day owner service, and 6-year enforcement limitations.

🏠 Home Hub

Statutory & Regulatory FAQs

What is the mandatory Notice of Furnishing under Ohio Revised Code § 1311.05?
If the property owner or contractor has recorded a Notice of Commencement, any subcontractor or material supplier who does not have a direct contract with the owner must serve a Notice of Furnishing within 21 calendar days after first performing labor or furnishing materials. Serving the notice preserves lien rights for all labor/materials furnished from the start; serving late only preserves lien rights for work done within 21 days prior to service and thereafter.
What are the recording deadlines for an Affidavit of Mechanics' Lien under ORC § 1311.06?
An Affidavit for Mechanics' Lien must be recorded with the county recorder: (1) Within 60 calendar days from the date of last labor/materials on residential 1- or 2-family dwellings; (2) Within 75 calendar days from the date of last labor/materials on commercial and industrial projects; (3) Within 120 calendar days for oil and gas wells.
What are the post-recording service and lawsuit deadlines in Ohio?
Under ORC § 1311.07, the claimant must serve a copy of the recorded affidavit on the property owner within 30 calendar days of recording (or post on premises within 10 days if service cannot be made). Under ORC § 1311.13, a mechanics lien continues in force for 6 years after recording, unless the owner serves a Notice to Commence Suit, which shortens the lawsuit deadline to 60 days!