North Carolina Mechanics Lien 120-Day Filing Auditor | N.C.G.S. § 44A-12

Audit statutory deadlines, Notice to Lien Agent (LiensNC), 120-day Claim of Lien on Real Property, and 180-day lawsuit enforcement under N.C.G.S. Chapter 44A.

🏠 Home Hub

Statutory & Regulatory FAQs

What is the mandatory deadline to record a Claim of Lien on Real Property in North Carolina?
Under N.C.G.S. § 44A-12(b), a Claim of Lien on Real Property must be filed with the Clerk of Superior Court in the county where the real property is located within 120 calendar days after the date of last furnishing of labor or materials at the site of the improvement by the person claiming the lien. Missing this deadline by even one day completely extinguishes the lien rights.
What is the role of the North Carolina Lien Agent (LiensNC)?
Under N.C.G.S. § 44A-11.1, for private projects costing $40,000 or more (except owner-occupied single-family residence additions), the owner must designate a Lien Agent through LiensNC. Potential lien claimants (contractors, subs, suppliers) must file a Notice to Lien Agent within 15 days of first furnishing labor or materials, or prior to the date the deed or deed of trust is recorded, to protect priority against third-party purchasers or construction lenders.
What is the statute of limitations to enforce a North Carolina mechanics lien?
Under N.C.G.S. § 44A-13(a), an action to enforce the Claim of Lien on Real Property (foreclosure lawsuit) must be commenced in the county where the property is situated within 180 days after the date of last furnishing of labor or materials. A notice of lis pendens must also be filed in every county where any part of the real property is located.