Audit mechanics lien perfection on North Carolina real property under N.C.G.S. § 44A-12. Calculate the mandatory 120-day county recording deadline, Lien Agent compliance (LiensNC), owner service, and the 180-day enforcement suit cutoff.
🔨 Project Dates & Lien Agent Information
Day 1 of both 120-day recording and 180-day suit clocks!
120-Day Filing Deadline
-
180-Day Lawsuit Deadline
-
Lien Priority Status
Senior
Statutory Procedural Findings:
Frequently Asked Questions (N.C.G.S. § 44A-12)
What is the deadline to file a Claim of Lien on Real Property in North Carolina?
Under N.C.G.S. § 44A-12(b), a Claim of Lien must be filed with the Clerk of Superior Court in the county where the property is located not later than 120 calendar days after the last date labor or materials were furnished. There are no statutory extensions, and late filing is a fatal jurisdictional defect.
What is the Notice to Lien Agent requirement in North Carolina?
On any commercial or residential project costing $30,000 or more (except renovations to an existing primary residence), the owner must appoint a Lien Agent through LiensNC.com. Potential lien claimants must file a Notice to Lien Agent within 15 days of first work to protect their lien priority against subsequent property sales or mortgage refinances.
How long does a claimant have to file an enforcement lawsuit in North Carolina?
Under N.C.G.S. § 44A-13, a lawsuit to enforce the lien must be filed within 180 days after the last date of furnishing labor or materials (NOT 180 days from the filing date). In addition, a Notice of Lis Pendens must be filed in each county where the property is situated.