Evaluate owner and general contractor demands for verified itemized statements under New York Lien Law § 38. Audit the strict 5-day response window, labor/material itemization standards, and court petitions to cancel liens.
📜 Demand & Lien Particulars
Day 1 of the strict 5-calendar-day response window.
Leave blank if no response has been served.
Under NY case law (Matter of 810 Flushing), incomplete lump sum requires detailed itemization.
5-Day Response Deadline
-
Lien Defense / Vacatur Risk
Low
Statement Sufficiency
Sufficient
Statutory Procedural Analysis:
Frequently Asked Questions (NY Lien Law § 38)
What is a Demand for an Itemized Statement under New York Lien Law § 38?
Section 38 enables an owner or general contractor to compel a mechanics lienor to provide a sworn, itemized breakdown of the labor, materials, and contract terms underlying the lien. It is a critical defense mechanism used to challenge inflated, fraudulent, or unsubstantiated mechanics liens in New York.
How many days does a lienor have to respond to a Section 38 demand?
The lienor has exactly 5 calendar days from receipt of the demand to serve a verified itemized statement. If the lienor fails to comply within 5 days, the owner or contractor may file a special proceeding in Supreme Court on not less than 2 days notice for an order directing compliance or canceling the lien.
Can a lump-sum contractor refuse to itemize under Section 38?
Under New York appellate precedent (Matter of 810 Flushing Co. and Matter of F.J.C. Cavo Constr.), if a lump-sum contract is 100% completed, the contractor does not need to itemize individual labor hours. However, if the contract was terminated, abandoned, or partially completed, the lienor MUST provide full itemization of labor and materials to support the quantum meruit value of the lien.