Under NMSA 1978 § 48-2-2.1, a preliminary Notice of Intent to Claim Lien is required on residential construction containing four or fewer dwelling units for contracts exceeding $5,000. It must be served within sixty (60) days of initially furnishing labor or materials. On commercial projects, no preliminary notice is required.
Under NMSA 1978 § 48-2-6, an original contractor (having a direct contract with the owner) must record their claim of lien within 120 days after the completion of their contract. All other claimants (subcontractors, laborers, material suppliers) must record within 90 days after the completion of the building or improvement.
Under NMSA 1978 § 48-2-2.1(B), if the preliminary notice is given after 60 days, lien rights are not entirely lost, but they are limited strictly to labor and materials furnished within the thirty (30) days prior to the date the late notice is actually served.
Under NMSA 1978 § 48-2-10, a mechanics lien remains valid for two (2) years from the date it is recorded with the county clerk. If judicial foreclosure proceedings are not commenced within two years, the lien expires and becomes void.