Who must serve preliminary notice in New Mexico and what is the deadline?

Under NMSA 1978 § 48-2-2.1, subcontractors and material suppliers who have a contract exceeding $5,000 on commercial projects (or on residential projects with more than 4 dwellings) and lack direct contractual privity with the owner or original contractor must serve a preliminary notice within 60 days of initially furnishing labor or materials.

What are the recording deadlines for an original contractor versus subcontractor in New Mexico?

Under NMSA 1978 § 48-2-6, an original contractor (direct contract with owner) must record a claim of lien with the county clerk within 120 days of completing the contract. All other claimants (subcontractors, sub-subcontractors, and materialmen) must record within 90 days after the completion of the building, improvement, or structure.

What is the statute of limitations to enforce a mechanics lien in New Mexico?

Under NMSA 1978 § 48-2-10, a mechanics lien expires unless proceedings to enforce it are commenced in district court within two (2) years after the claim of lien is recorded in the county clerk's office. If credit is given, suit must be filed within two years after the expiration of the credit term.