Nevada NRS Chapter 108 Mechanics Lien Auditor

31-Day Preliminary Notice (§ 108.245), 40-Day NOC / 90-Day Recording & 6-Month Foreclosure

Claim & Project Parameters

Nevada Lien Deadline Tracker

31-Day Preliminary Notice Deadline: -
Statutory Recording Window (NRS 108.226): -
County Recorder Lien Filing Deadline: -
30-Day Verified Copy Service to Owner (§ 108.227): -
6-Month Judicial Foreclosure Lawsuit Deadline: -

Nevada Mechanics Lien FAQs

When is a Preliminary Notice of Right to Lien required in Nevada?
Under NRS 108.245, a subcontractor, materialman, or equipment supplier (anyone without a direct contract with the owner) must deliver a written Notice of Right to Lien to the owner of the property and prime contractor within thirty-one (31) calendar days after first furnishing labor or materials to the project.
What is the recording deadline for a Notice of Lien in Nevada under NRS 108.226?
Under NRS 108.226, if a Notice of Completion is properly recorded by the owner, all lien claimants must record their Notice of Lien within forty (40) days. If no Notice of Completion was recorded, the lien must be recorded within ninety (90) days from the completion of the work or last delivery of material.
How long is a Nevada mechanics lien valid before a foreclosure suit must be filed?
Under NRS 108.233, an action to foreclose a mechanics lien must be commenced in district court within six (6) calendar months after the Notice of Lien was recorded. Failure to file within 6 months extinguishes the lien entirely.