Nebraska Construction Lien Act (Neb. Rev. Stat. §§ 52-125 to 52-159)

Nebraska Construction Lien Act Auditor

Audit Nebraska construction lien compliance under Neb. Rev. Stat. Chapter 52. Calculate the 120-day Register of Deeds recording deadline, 10-day owner notice, and 2-year judicial enforcement window.

Project & Lien Particulars

Triggers the 120-day recording window under Neb. Rev. Stat. § 52-137.
Triggers 10-day owner notice and 2-year statute of limitations.

Statutory Compliance Audit

STATUTORY RECORDING WINDOW OPEN
Claimant is within the mandatory 120-day recording deadline.
Lien Claim Principal
$55,000
Days to 120-Day Cutoff
65 Days
Recording Deadline
Nov 10, 2026
Owner Notice Cutoff
10 Days

Procedural Deadlines & Statutory Windows

County Register of Deeds Recording
Must record within 120 calendar days under Neb. Rev. Stat. § 52-137.
Mandatory Service on Owner (10-Day Rule)
Must send recorded copy to owner within 10 days under Neb. Rev. Stat. § 52-135(3).
Judicial Enforcement Limitation
Action to foreclose must be filed within 2 years under Neb. Rev. Stat. § 52-140.
🏠 Home Hub

Frequently Asked Questions (Nebraska Construction Lien Act)

What is the recording deadline under the Nebraska Construction Lien Act?
Under Neb. Rev. Stat. § 52-137, a claimant's lien must be recorded with the register of deeds of the county where the real estate is located no later than 120 days after the claimant's final furnishing of services or materials.
Is notice required to be served on the owner after recording a lien in Nebraska?
Yes. Under Neb. Rev. Stat. § 52-135(3), the claimant must send a copy of the recorded lien to the contracting owner within 10 days after recording the lien. Failure to serve this notice does not immediately void the lien, but it prevents the claimant from recovering attorney's fees and costs.
What is the statute of limitations to enforce a construction lien in Nebraska?
Under Neb. Rev. Stat. § 52-140, judicial proceedings to enforce a construction lien must be instituted within 2 years after the recording of the lien. If no judicial enforcement action is filed within 2 years, the lien automatically lapses.
Can an owner shorten the 2-year enforcement window in Nebraska?
Yes. Under Neb. Rev. Stat. § 52-140(2), the contracting owner may serve a formal written demand upon the claimant to institute judicial proceedings within 30 days. If the claimant fails to commence suit within 30 days after receipt of the demand, the lien is extinguished.