Frequently Asked Questions (Nebraska Construction Lien Act)
What is the recording deadline under the Nebraska Construction Lien Act?
Under Neb. Rev. Stat. § 52-137, a claimant's lien must be recorded with the register of deeds of the county where the real estate is located no later than 120 days after the claimant's final furnishing of services or materials.
Is notice required to be served on the owner after recording a lien in Nebraska?
Yes. Under Neb. Rev. Stat. § 52-135(3), the claimant must send a copy of the recorded lien to the contracting owner within 10 days after recording the lien. Failure to serve this notice does not immediately void the lien, but it prevents the claimant from recovering attorney's fees and costs.
What is the statute of limitations to enforce a construction lien in Nebraska?
Under Neb. Rev. Stat. § 52-140, judicial proceedings to enforce a construction lien must be instituted within 2 years after the recording of the lien. If no judicial enforcement action is filed within 2 years, the lien automatically lapses.
Can an owner shorten the 2-year enforcement window in Nebraska?
Yes. Under Neb. Rev. Stat. § 52-140(2), the contracting owner may serve a formal written demand upon the claimant to institute judicial proceedings within 30 days. If the claimant fails to commence suit within 30 days after receipt of the demand, the lien is extinguished.