Construction & Mechanics Lien Law

Montana Construction Lien Statutory Compliance Auditor | MCA § 71-3-5

Audit Montana construction lien compliance under MCA Title 71, Chapter 3, Part 5: mandatory 20-day Notice of Right to Claim a Lien (§ 71-3-531), 90-day recording deadline in County Clerk and Recorder (§ 71-3-535), 5-day post-recording notice to owner (§ 71-3-534), and 2-year lawsuit limitation period (§ 71-3-562).

Deadline: 20 calendar days from first furnishing
Deadline: 90 calendar days from last furnishing

Statutory & Regulatory Guidance

Under MCA § 71-3-531, any person who furnishes services or materials pursuant to a real estate improvement contract must give notice of the right to claim a construction lien to the contracting owner. The notice must be served by personal service or certified mail and recorded with the County Clerk and Recorder within twenty (20) days of first furnishing services or materials. Direct prime contractors with the owner are exempt.

Under MCA § 71-3-535, the construction lien must be recorded in the office of the County Clerk and Recorder within ninety (90) days after the final furnishing of services or materials by the lien claimant, or within 90 days after the owner records a notice of completion.

Under MCA § 71-3-534, within five (5) business days after recording the lien, the claimant must serve a copy of the lien upon the owner. Under MCA § 71-3-562, an action to enforce the lien must be commenced in District Court within two (2) years from the date the lien was recorded.