Project & Filing Timeline
Statutory Formalities
Statutory Audit & Deadlines
MISSISSIPPI LIEN STATUTORILY VALID
Lien was recorded within 90 days with Chancery Clerk. Enforcement lawsuit must be filed within statutory limits.
Recording Elapsed Days
70 Days (Max 90)
Filing Deadline Limit
90 Days (§ 85-7-405)
Enforcement Lawsuit Deadline
Nov 06, 2025
Lis Pendens Mandated?
YES (§ 85-7-421)
Mississippi Statutory Checklist
| Statutory Mandate | Miss. Code Ann. | Compliance Status |
|---|
Mississippi Mechanics' Lien Legal FAQ
What is the pre-lien notice requirement in Mississippi for claimants not in privity with the owner?
Under Miss. Code Ann. § 85-7-407, any subcontractor or materialman not in direct contractual privity with the owner must serve a written 'Notice to Lien Contemplated' on the contractor and owner within thirty (30) days of first furnishing labor, services, or materials to the project.
What is the deadline to record a mechanics' lien in Mississippi?
Under Miss. Code Ann. § 85-7-405, a claim of lien must be filed for recording in the office of the clerk of the chancery court of the county where the real estate is located within ninety (90) days after the claimant's last work performed or materials furnished.
What is the statute of limitations to enforce a Mississippi mechanics' lien?
Under Miss. Code Ann. § 85-7-421, a lien action must be commenced in court within one hundred eighty (180) days after the date the lien was filed with the chancery clerk. A lis pendens notice must also be filed with the chancery clerk within this 180-day period.
How does a Notice of Contest of Lien affect Mississippi lien deadlines?
Under Miss. Code Ann. § 85-7-423, an owner or contractor may file a statutory Notice of Contest of Lien with the chancery clerk and serve it on the claimant. This dramatically accelerates the enforcement lawsuit deadline: the claimant must commence a lawsuit to enforce the lien within sixty (60) days after the notice was filed, or the lien is automatically discharged.