Miss. Code § 85-7-401

Mississippi Mechanics' Lien (Miss. Code § 85-7) Statutory Auditor

Miss. Code Ann. § 85-7-401 through § 85-7-433 Recording, Lis Pendens & Lawsuit Audit

Starts 90-day chancery filing clock
Filed in lis pendens record within 90 days
Accelerates lawsuit deadline to 60 days
90-Day Chancery Deadline --
Foreclosure Lawsuit Deadline --
Lawsuit Deadline Type Standard 180 Days
Claimed Principal $45,000.00
Recording Office Chancery Clerk
Statutory Status PERFECTED

Mississippi Construction Lien Legal Directives:

🏠 Home Hub

Statutory Compliance Frequently Asked Questions

Under Miss. Code Ann. § 85-7-407, any subcontractor or material supplier who does not have a direct contract with the property owner must provide a written Pre-Lien Notice to the owner within 30 days of first commencing work or delivering materials. Failure to provide this pre-lien notice forfeits lien rights against the owner to the extent the owner has already paid the prime contractor.

\n

Under Miss. Code Ann. § 85-7-405, a verified Claim of Lien must be filed with the chancery clerk of the county where the real property is located within 90 days after the claimant's last date of labor, services, or materials furnished. A copy of the lien must also be served upon the property owner within two business days after filing.

\n

Under Miss. Code Ann. § 85-7-423, the standard deadline to file an enforcement lawsuit is 180 days from the date of filing the claim of lien. However, an owner or contractor can file a formal Notice of Contest of Lien in the chancery clerk's office and serve it on the claimant. Once served, the lawsuit deadline is ACCELERATED from 180 days down to exactly 60 days. Failure to commence suit within 60 days of the contest notice extinguishes the lien automatically.