Michigan Construction Lien Notice of Furnishing & Recording Auditor | MCL § 570.1101
Audit Michigan Construction Lien Act deadlines: 20-day Notice of Furnishing (MCL 570.1109), 90-day Claim of Lien recording (MCL 570.1111), 15-day service, and 1-year foreclosure lawsuits.
Statutory Provisions & Frequently Asked Questions
What is the 20-day Notice of Furnishing rule under Michigan MCL § 570.1109?
Under MCL § 570.1109(1), a subcontractor or supplier who contracts to provide an improvement to real property must serve a Notice of Furnishing upon the designee and general contractor within 20 calendar days after first furnishing labor or material. Unlike some states where failure is fatal, in Michigan late service preserves lien rights for work done, except to the extent the owner made payments to the general contractor before receiving the notice.
What is the recording and service deadline for a Michigan Claim of Lien?
Under MCL § 570.1111(1), a Claim of Lien must be recorded in the register of deeds for each county where the real property is situated within 90 days after the date on which the last labor or material was furnished. Furthermore, under Section 1111(5), a copy of the recorded claim of lien must be served on the owner or designee within 15 calendar days after recording, and a proof of service must be filed.
What is the statute of limitations to foreclose a Michigan construction lien?
Under MCL § 570.1117(1), proceedings to enforce a construction lien through foreclosure in the circuit court must be commenced not later than 1 year after the date the Claim of Lien was recorded. If no foreclosure action and notice of lis pendens are filed within 1 year, the lien is extinguished by operation of law.