Can a homeowner claim the Michigan Homeowner Construction Lien Recovery Fund? +
The former state recovery fund was repealed. Today, under MCL 570.1118a, an owner of residential property who has paid the general contractor in full pursuant to a sworn statement is protected against subcontractor liens.
Does punch list work extend the 90-day recording deadline in Michigan? +
No. Michigan courts hold that gratuitous, warranty, or minor corrective work performed solely to revive an expired lien period does not extend the statutory 90-day window under MCL 570.1111.
What happens if a sworn statement is not provided under MCL 570.1110? +
Under MCL 570.1110(8), until the contractor provides the sworn statement, the contractor has no right of action or lien against the owner or lessee on account of the contract.