Calculate and audit Massachusetts mechanics lien recording deadlines under M.G.L. c. 254: Section 2 (GC) / Section 4 (Sub) Notice of Contract, 90-day Statement of Amount Due, and 90-day enforcement complaint.

🏠 Home Hub

Statutory & Regulatory FAQs

What is the two-step perfection process under Massachusetts mechanics lien law (M.G.L. c. 254)?
Massachusetts requires a strict two-step recording procedure: Step 1: Record a Notice of Contract in the Registry of Deeds before the earliest of (a) 60 days after recording a notice of substantial completion, (b) 90 days after recording a notice of termination, or (c) 90 days after the claimant or anyone through them last performed or furnished labor or materials; Step 2: Record a Statement of Amount Due under Section 8 within 30 days after the last day on which the Notice of Contract could have been filed.
What is the difference between Section 2 (General Contractor) and Section 4 (Subcontractor) liens?
Under M.G.L. c. 254 § 2, a general contractor has a lien based on a written contract with the owner. Under § 4, a subcontractor or supplier (without owner privity) has a lien based on a written subcontract, but the subcontractor's lien is limited to the amount owed by the owner to the general contractor at the time the owner receives actual notice of the recording of the subcontractor's Notice of Identification or Notice of Contract.
What is the deadline to file a lawsuit to enforce a Massachusetts mechanics lien?
Under M.G.L. c. 254 § 11, the lien is permanently dissolved unless the claimant files a civil action in the Superior Court (or District Court) within 90 days after the recording of the Statement of Amount Due. An attested copy of the complaint must also be recorded in the Registry of Deeds within 30 days of filing the lawsuit.