Maine Mechanics' Lien Statutory Compliance Auditor | 10 M.R.S. Chapter 603
Audit Maine mechanics' and materialmen's lien compliance under 10 M.R.S. Chapter 603: 90-day lien certificate recording deadline in the County Registry of Deeds (10 M.R.S. § 3253), 120-day judicial foreclosure lawsuit deadline in Superior or District Court (10 M.R.S. § 3255), bona fide purchaser protections, and owner consent requirements.
Statutory Compliance Frequently Asked Questions
Under 10 M.R.S. § 3253, a claimant who does not contract directly with the property owner must file in the Registry of Deeds for the county or district where the building or land is situated a true statement of the amount due, with all just credits given, together with a description of the property and the owner's name, within ninety (90) days after ceasing to labor or furnish materials.
Under 10 M.R.S. § 3255, the lien is dissolved unless an action to enforce it is commenced in the Superior Court or District Court within one hundred twenty (120) days after the last labor or materials are furnished. Recording the certificate of lien under § 3253 preserves the lien, but filing the complaint within 120 days is mandatory to prevent automatic dissolution.
YES. Under 10 M.R.S. § 3253, the lien cannot be enforced against any property conveyed to a bona fide purchaser for valuable consideration without actual or constructive notice unless the certificate of lien was recorded in the Registry of Deeds prior to the recording of the deed to the bona fide purchaser.