La. R.S. 9:4801 Construction Privilege & Recording Calculator
Within statutory recording period under La. R.S. 9:4822.
Under La. R.S. 9:4811, if the general contract exceeds $100,000, the general contractor must file a written Notice of Contract in the mortgage records of the parish where the work is to be performed before any work begins. Failure to timely file forfeits the contractor's statutory privilege against third parties and alters subcontractor filing deadlines.
Under La. R.S. 9:4822: (1) If a Notice of Contract was properly filed and a Notice of Termination is filed, claimants have 30 days after the filing of the Notice of Termination to record their Statement of Claim; (2) If no Notice of Contract was filed, subcontractors, laborers, and materialmen have 60 days after the filing of a Notice of Termination or substantial completion of the work.
Under La. R.S. 9:4823, a privilege granted by the LPWA is extinguished unless an action to enforce it is commenced in parish district court within one (1) year after the date of filing of the Statement of Claim and Privilege, and a Notice of Lis Pendens is recorded.