Kentucky KRS Chapter 376 Mechanics Lien Auditor
Audit compliance with Kentucky Revised Statutes Chapter 376, verify tiered preliminary notice deadlines (75 vs 120 days per KRS 376.010), track 6-month county clerk recording deadlines, and enforce 12-month foreclosure lawsuit limits.
Mandatory Kentucky Formalities
Statutory & Regulatory FAQs
What preliminary notice is required to preserve mechanics lien rights in Kentucky?
Under KRS 376.010(3), any person who did not contract directly with the property owner must give written notice to the owner or owner's agent within: (1) 75 days on claims amounting to $1,000 or less; or (2) 120 days on claims amounting to more than $1,000, measured from the last day labor or materials were furnished. For owner-occupied single- or double-family residences, notice must be given prior to the owner making final payment to the prime contractor (KRS 376.010(4)).
What is the statutory deadline for recording a mechanics lien in Kentucky?
Under KRS 376.080(1), a lien claimant must record a verified statement of lien in the office of the county clerk of the county in which the property is situated within six months after the claimant ceases to labor or furnish materials on the project.
Must a copy of the recorded lien statement be sent to the property owner?
Yes. Under KRS 376.080(1), within seven days after recording the lien statement with the county clerk, the claimant must mail a copy of the statement by regular mail to the property owner at their last known address.
How long does a claimant have to initiate a foreclosure lawsuit in Kentucky?
Under KRS 376.090(1), a mechanics lien is dissolved and void unless an action to enforce the lien is commenced in the appropriate court within 12 months from the date the lien statement was recorded with the county clerk.