Kentucky Mechanics' Lien (KRS Chapter 376) Statutory Auditor
KRS § 376.010 - § 376.090 Preliminary Notice, County Recording & Lawsuit Timeline
Kentucky Mechanics' Lien Legal Directives:
Statutory Compliance Frequently Asked Questions
Under KRS § 376.010(3), any person who has not contracted directly with the owner (subcontractors, materialmen) must give written notice to the owner of the property of intent to hold the property liable for a lien: (1) Within 75 days after the last item of material or labor is furnished, if the total claim is $1,000 or less, or if the property is an owner-occupied single or double family dwelling; or (2) Within 120 days after the last item, if the claim exceeds $1,000 on other commercial or non-owner-occupied property. Failure to give this notice forfeits the lien.
Under KRS § 376.080, any claimant (both prime contractors and subcontractors) must file a verified statement of lien in the office of the county clerk of the county in which the property is situated within 6 months after the claimant ceases to labor or furnish materials. A copy of the statement must also be mailed by regular mail to the property owner within 7 days after filing with the county clerk.
Under KRS § 376.090, any mechanics' lien is completely dissolved unless an action to enforce the lien is commenced in the circuit court within 12 months from the date of filing the statement of lien in the county clerk's office. Failure to file suit within 12 months renders the lien void.