Kansas Mechanics' & Materialman's Lien Auditor | K.S.A. Chapter 60, Article 11
Audit Kansas mechanics' and materialman's lien statutory compliance under K.S.A. Chapter 60, Article 11: 4-month (general contractor, K.S.A. § 60-1102) vs 3-month (subcontractor, K.S.A. § 60-1103) lien statement recording with the District Court Clerk, mandatory service of copy on owner via certified mail, residential warning statement, and 1-year foreclosure lawsuit deadline (K.S.A. § 60-1105).
Statutory Compliance Frequently Asked Questions
Under K.S.A. § 60-1102, a general contractor (one contracting directly with the owner) must record the lien statement with the Clerk of the District Court in the county where the property is located within four (4) months after the date material, equipment, or supplies were last furnished or labor performed. Under K.S.A. § 60-1103, a subcontractor or supplier must record within three (3) months, though this may be extended to 5 months if the claimant files a notice of intent to perform prior to recording.
Under K.S.A. § 60-1103(a), subcontractors must serve a copy of the lien statement on the property owner by certified mail, restricted delivery, return receipt requested, or by personal service by the sheriff or process server. If the owner cannot be found within the county, an affidavit of service stating reasonable diligence must be filed with the court.
Under K.S.A. § 60-1105, an action to foreclose and enforce a mechanics' lien must be commenced in District Court within one (1) year from the date the lien statement was filed with the Clerk of the District Court. Failure to file suit within one year renders the lien completely void and unenforceable as an encumbrance on the title.