Under K.S.A. § 60-1102, a general contractor (having a direct contract with the property owner) must file a lien statement in the office of the clerk of the district court in the county where the property is located within four (4) months after the date material, equipment, or labor was last furnished.
Under K.S.A. § 60-1103, a subcontractor or supplier must file their lien statement within three (3) months after the date material, equipment, or labor was last furnished. However, if the subcontractor files a Notice of Intent to Perform before completing work, the deadline may be extended to five (5) months.
Under K.S.A. § 60-1103(a), the claimant must serve a copy of the lien statement upon the property owner by certified mail with return receipt requested or by personal service, and an affidavit of service must be filed with the district court clerk.
Under K.S.A. § 60-1105, an action to enforce a mechanics lien must be filed in the district court within one (1) year from the date the lien statement was filed. If a foreclosure lawsuit is not commenced within one year, the lien expires and becomes completely unenforceable.