Under Iowa Code § 572.13A and § 572.13B, Iowa operates a centralized electronic statewide database called the Mechanics' Notice and Lien Registry (MNLR), administered by the Iowa Secretary of State. For residential construction projects, all mechanics' liens, notices of commencement of work, and subcontractor preliminary notices MUST be posted electronically on the MNLR website (not filed with the county recorder) to be legally valid.
For residential projects: (1) General contractors must post a Notice of Commencement of Work to the MNLR within 10 days of commencing work; (2) Subcontractors must post a Preliminary Notice to the MNLR prior to the general contractor being fully paid; (3) All claimants must post their verified mechanics' lien statement within 90 days after the last date of furnishing labor or materials to preserve full priority against purchasers and lenders.
Under Iowa Code § 572.28, a property owner or contractor may serve a formal written 30-day demand upon a lien claimant requiring them to commence a foreclosure lawsuit within 30 days. If the claimant fails to file an action in the Iowa District Court within 30 days of receiving the demand, the lien is completely forfeited and canceled as a matter of law.