Indiana Mechanics Lien Statutory Compliance Auditor

Audit Indiana mechanics lien perfection under Ind. Code § 32-28-3: 30/60-day residential pre-lien notices, 60-day residential vs 90-day commercial recording, and 1-year lawsuit limitations.

Governs pre-lien notice requirements and recording deadlines.
Non-privity residential claimants must record pre-lien notice.
Mandatory condition precedent on residential homes.
Starts the 60-day (residential) or 90-day (commercial) clock.
Principal claim for unpaid labor, materials, or equipment.
Shortens foreclosure suit deadline to 30 calendar days!
Audit Completed
Pre-Lien Notice Status
Compliant
County Recording Window
60 Calendar Days
County Recording Deadline
Calculating...
Court Lawsuit Deadline
1 Year Post-Recording
Enforceable Lien Value
$48,000.00

Indiana Mechanics Lien Statutory Guidance

When is a pre-lien notice required on residential projects in Indiana under Ind. Code § 32-28-3-1(i)?
Under Indiana Code § 32-28-3-1(i), anyone furnishing labor, materials, or equipment for an owner-occupied single or double-family dwelling who does not have direct contract privity with the owner must record a written Pre-Lien Notice in the County Recorder's office and serve a copy on the owner: (1) within thirty (30) days of first work on an existing dwelling; or (2) within sixty (60) days of first work on new residential construction. Failure to timely record and serve this pre-lien notice permanently forfeits all mechanics lien rights.
What are the statutory recording deadlines for an Indiana Sworn Statement and Notice of Intention to Hold Lien?
Under Ind. Code § 32-28-3-3, a sworn statement and notice of intention to hold a lien must be recorded in the County Recorder's office: (1) within sixty (60) calendar days after the last performance of labor or furnishing of materials for Class 2 residential structures (1-2 family homes); or (2) within ninety (90) calendar days for commercial, industrial, or non-residential properties.
What is the statute of limitations to enforce an Indiana mechanics lien under § 32-28-3-6?
Under Ind. Code § 32-28-3-6, an action to enforce an Indiana mechanics lien must be commenced in Circuit or Superior Court within one (1) year after the date the sworn statement and notice of intention to hold a lien was recorded. However, if the owner serves a written Notice to Commence Suit under § 32-28-3-10, the claimant must commence suit within thirty (30) days of receipt, or the lien is automatically void.