Indiana Mechanics Lien Commercial vs Residential Notice & Filing Auditor | Ind. Code § 32-28-3
Audit Indiana mechanics lien statutory deadlines under Ind. Code § 32-28-3: Commercial 90-day recording, Residential 60-day recording, pre-lien notices, and 1-year foreclosure lawsuits.
Statutory Provisions & Frequently Asked Questions
What is the difference between commercial and residential lien recording deadlines in Indiana?
Under Indiana Code § 32-28-3-3: (1) For commercial, industrial, and utility projects, the sworn statement and notice of intention to hold a lien must be recorded in the county recorder's office within 90 calendar days after performing the labor or furnishing materials; (2) For residential construction (Class 2 structures such as single-family or two-family homes), the recording deadline is strictly 60 calendar days.
What is the residential pre-lien notice requirement under Ind. Code § 32-28-3-1?
For work on an owner-occupied single or double-family dwelling, a subcontractor or supplier must deliver a written notice of intention to hold a lien to the owner within 30 days of first furnishing materials or labor (or within 60 days if the dwelling is new residential construction). Failure to serve this preliminary notice eliminates the claimant's lien rights.
What is an owner's 30-day Notice to Foreclose under Ind. Code § 32-28-3-10?
A property owner or other interested person may serve a formal written notice on the lienholder requiring the lienholder to commence an action to enforce the lien. If the lienholder fails to file a foreclosure lawsuit within 30 days after receiving this notice, the lien is discharged and entirely void.