Statutory Compliance Engine for 770 ILCS 60/24, 60/5, 60/7 & 60/9
Under the Illinois Mechanics Lien Act (770 ILCS 60/1 et seq.), mechanics liens are in derogation of common law and must be strictly construed with respect to all procedural statutory steps leading up to the perfection of the lien. Illinois courts routinely strike liens where the 90-day subcontractor notice is late by even a single day.
Service on Mortgage Lender: Section 24 explicitly mandates notice not only to the owner of record but also to the construction lender or mortgagee whose mortgage is recorded. Failure to serve the lender impairs the lienholder's priority against loan proceeds and subsequent foreclosure distributions.
Owner-Occupied Residential Protections (770 ILCS 60/5 & 60/21): Homeowners of single-family residences enjoy heightened protections. A subcontractor must serve notice within 60 days of starting work. If served after 60 days, the lien attaches only to sums remaining unpaid by the owner to the primary contractor at the moment notice is received. If the owner has paid the general contractor in full in good faith, the subcontractor's lien against the home is extinguished.