Idaho Code (Title 45, Chapter 5)

Idaho Mechanics' Lien Law Auditor

Audit Idaho mechanics' lien statutory compliance under Idaho Code § 45-501 et seq. Enforce the 90-day recording deadline, mandatory 24-hour owner notice (§ 45-507(5)), and 6-month foreclosure period.

Project & Lien Particulars

Triggers 90-day recording cutoff under Idaho Code § 45-507.
County Recorder filing date. Triggers 24-hour owner notice rule.
Must be within 24 hours of recording to preserve attorney's fees (§ 45-507(5)).

Statutory Compliance Audit Results

STATUTORY RECORDING TIMELY
Claim recorded within 90-day statutory window.
Lien Principal Claim
$62,500
Days to 90-Day Cutoff
34 Days
24-Hour Notice Status
Compliant
6-Month Lawsuit Limit
Dec 15, 2026

Idaho Statutory Rules (Idaho Code Title 45)

90-Day County Recording Window
Must record verified claim with County Recorder within 90 days under § 45-507.
Mandatory 24-Hour Owner Notice (§ 45-507(5))
Must serve or mail copy to owner within 24 hours of filing to preserve legal fees.
6-Month Foreclosure Statute of Limitations
Action to enforce lien in district court must be filed within 6 months (§ 45-510).
🏠 Home Hub

Frequently Asked Questions (Idaho Mechanics' Liens)

What is the statutory deadline to record a mechanics' lien in Idaho?
Under Idaho Code § 45-507, all mechanics' lien claimants (general contractors, subcontractors, and material suppliers) must file a claim of lien with the county recorder of the county where the property is located within 90 days after the completion of the labor or services, or the cessation of the furnishing of materials.
What is Idaho's mandatory 24-hour owner notice requirement?
Under Idaho Code § 45-507(5), a claimant must serve or mail a copy of the recorded claim of lien to the owner or reputed owner within 24 hours of filing the claim with the county recorder. Service must be made personally or by certified mail. Failure to serve this copy within 24 hours bars the claimant from recovering attorney's fees and costs.
What is the statute of limitations to enforce a mechanics' lien in Idaho?
Under Idaho Code § 45-510, a mechanics' lien remains valid for only 6 months after the claim of lien has been filed, unless judicial foreclosure proceedings are commenced in the district court within that 6-month period.
Can an extension be filed to prolong the 6-month lawsuit deadline in Idaho?
Yes. Under Idaho Code § 45-510, if payment credit is given and the terms are endorsed on the recorded lien, the foreclosure deadline may be extended to 6 months after the expiration of such credit, but not to exceed 2 years from the date of work completion.