Frequently Asked Questions (Idaho Mechanics' Liens)
What is the statutory deadline to record a mechanics' lien in Idaho?
Under Idaho Code § 45-507, all mechanics' lien claimants (general contractors, subcontractors, and material suppliers) must file a claim of lien with the county recorder of the county where the property is located within 90 days after the completion of the labor or services, or the cessation of the furnishing of materials.
What is Idaho's mandatory 24-hour owner notice requirement?
Under Idaho Code § 45-507(5), a claimant must serve or mail a copy of the recorded claim of lien to the owner or reputed owner within 24 hours of filing the claim with the county recorder. Service must be made personally or by certified mail. Failure to serve this copy within 24 hours bars the claimant from recovering attorney's fees and costs.
What is the statute of limitations to enforce a mechanics' lien in Idaho?
Under Idaho Code § 45-510, a mechanics' lien remains valid for only 6 months after the claim of lien has been filed, unless judicial foreclosure proceedings are commenced in the district court within that 6-month period.
Can an extension be filed to prolong the 6-month lawsuit deadline in Idaho?
Yes. Under Idaho Code § 45-510, if payment credit is given and the terms are endorsed on the recorded lien, the foreclosure deadline may be extended to 6 months after the expiration of such credit, but not to exceed 2 years from the date of work completion.