Georgia Mechanics Lien Statutory FAQ
When is a Notice to Contractor (NTC) mandatory in Georgia?
Under O.C.G.A. § 44-14-361.5, if the property owner or general contractor timely records a Notice of Commencement in the county real estate records, any subcontractor or material supplier who does not have direct contractual privity with the prime contractor MUST send a written Notice to Contractor within thirty (30) days from the first day labor or materials are furnished. Failure to deliver this 30-day NTC completely strips the claimant of all statutory mechanics lien rights.
What is the statutory deadline to record a Claim of Lien in Georgia?
Under O.C.G.A. § 44-14-361.1(a)(2), a Claim of Lien must be filed for recording in the Office of the Clerk of the Superior Court of the county where the real property is located within ninety (90) calendar days after the completion of the work or the last day materials were furnished. In addition, within two (2) business days of filing, a copy of the lien must be sent to the owner by certified or registered mail or statutory overnight delivery.
What is the statute of limitations to enforce a Georgia mechanics lien?
Under O.C.G.A. § 44-14-361.1(a)(3), a lawsuit to enforce a mechanics lien must be commenced within 365 days (1 year) from the date the claim of lien was filed for recording. Furthermore, under subsection (a)(4), a Notice of Commencement of Lien Action must be filed in the county deed records within thirty (30) days after filing the lawsuit.